Waste Management Plan
for Tung Chung New Town Extension (West)
(EP No. EP-519/2016)
January 2026


1. Project Description
The development of Tung Chung New Town Extension (TCNTE), comprising Tung Chung East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project aiming to provide land to meet the future housing economic and social development needs of Hong Kong. Due to the fact that the proposed works are geographically separated, the implementation of mega-scale Project is divided into two packages, namely TCE and TCW respectively. In accordance with the tight delivery programme, the Project will be implemented in phases under separate contracts for the developments of TCE and TCW. This Plan only covers the works in TCW. Waste Management Plan for TCE can be found at dedicated project website: http://env.tcnte.hk/ep-submissions.html.
2. Scope of Works for Tung Chung New Town Extension
The Tung Chung New Town Extension project (the Project) comprises the following elements:
(i) reclamation of the seabed by a non-dredged method at TCE to form a total of about 130 hectares of land;
(ii) construction of about 4.9 kilometers of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three circulation drains and a seawater intake at TCE;
(iii) provision of infrastructure for Tung Chung Area 58, including construction of a single two-lane road with a footpath and the associated utility works;
(iv) site formation works at TCW;
(v) construction of the River Park including a visitor centre at TCW;
(vi) construction of proposed open space;
(vii) construction of sustainable urban drainage systems at TCW;
(viii) construction of roads, footpaths, cycle tracks and the associated junction / road improvement works;
(ix) engineering infrastructure works covering drainage, sewerage, waterworks (including a fresh water service reservoir, a salt water service reservoir and a salt water pumping station), common utility tunnels and landscaping works; and
(x) implementation of environmental mitigation measures and environmental monitoring and audit programme for the works.
3. Implementation Programme
The Contract No NL/2020/05 – Tung Chung New Town
Extension – Site Formation and
Infrastructure Works at Ma Wan Chung (i.e. Contract 5) at TCW has been awarded
in May 2021 and the major construction work is scheduled for completion in mid
of 2026. The main contractor for Contract No. NL/2020/05 is Build King – Richwell
Civil Joint Venture (BKRCJV).
The Contract No NL/2020/06
– Tung Chung New Town Extension – Site Formation and Infrastructure Works at
Tung Chung Valley, Phase 1 (i.e. Contract 6) at TCW has been awarded in May
2021 and the major construction work is scheduled for completion in 2026. The
main contractor for Contract No. NL/2020/06 is China Railway Group Limited
(CREC).
The Contract No
NL/2023/10 – Tung Chung New Town Extension – Infrastructure Works at Tung Chung
Valley, Yu Tung Road and Ma Wan Cheung (i.e. Contract 10) at TCW has been
awarded in October 2025 and is scheduled for completion in 2029. The main
contractor for Contract No. NL/2023/10 is CREC Joint Venture (CRECJV).
The Entrustment
Agreement No. ENT/TUE/001 – Construction of Infrastructure Works in the Tung
Chung New Town Extension Area (i.e. Entrusted Works) has been awarded in June
2025 and is scheduled for completion in 2028. The main contractor for
Entrusted Works is Bouygues Dragages (1201) Joint Venture (BDJV).
4.
Submission under EP
In view that only the
site formation and infrastructure works at Ma Wan Chung (i.e. Contract 5) and
Tung Chung Valley, Phase 1 (Contract 6), Area 33, (Entrusted Works) and
Infrastructure Works at Tung Chung Valley, Yu Tung Road and Ma Wan Chung
(Contract 10) at TCW have commenced, this submission is prepared based on the
latest information of Contract 5, Contract 6, Entrusted Works and Contractor
10. The submission shall be updated before commencement of construction of the
respective contracts for the site formation and infrastructure works at TCW
according to the relevant requirements contained in the EM&A Manual, EIA
Report and EP.
The Waste Management
Plan for Contract 5 is provided in Attachment I below.
The Waste Management
Plan for Contract 6 is provided in Attachment II below.
The Waste Management
Plan for Contract 10 is provided in Attachment III
below.
The Waste Management Plan
for Entrusted Works is provided in Attachment IV below.