1          introduction.. 3

1.1         PROJECT BACKGROUND.. 3

1.2         SCOPE OF WORKS. 3

1.3         IMPLEMENTATION PROGRAMME.. 4

 

 

List of Appendices

 

Appendix A

Construction Works Schedule

Appendix B

Site Location Plan

 

 


1                    introduction

The plan is prepared by China Railway Engineering Group Limited (known as CREC) in accordance with the Condition 2.12 of the Environmental Permit No. EP-519/2016 dated 09/08/2016.

 

1.1              PROJECT BACKGROUND

The development of Tung Chung New Town Extension (TCNTE), comprising Tung Chung East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project aiming to provide land to meet the future housing economic and social development needs of Hong Kong. Due to the fact that the proposed works are geographically separated, the implementation of mega-scale Project is divided into two packages, namely TCE and TCW respectively. In accordance with the tight delivery programme, the Project will be implemented in phases under separate contracts for the developments of TCE and TCW.

 

1.2               SCOPE OF WORKS

The works to be executed under the Contract NL/2020/06 involve site formation and infrastructure works at Tung Chung Valley under Tung Chung New Town Extension, as described below:

(a)     Site clearance (including, but not limited to, the demolition of the existing building structures);

(b)     Site formation works for Area 42 and Area 46 with associated geotechnical works;

(c)     Improvement works for Chung Mun Road and Shek Mun Kap Road with associated infrastructural and geotechnical works;

(d)     Provision of infrastructural works at Yu Tung Road;

(e)     Construction of Road L29 and Road L30 with associated infrastructural and geotechnical works;

(f)      Provision of attenuation & treatment ponds;

(g)     Provision of a Common Utility Trough and box culvert along Road L29;

(h)     Provision of Pumping Stations;

(i)       Construction of a proposed River Park with Visitor Centre, footbridge across river and other associated facilities;

(j)       Provision of roadside Sustainable Urban Drainage System (SUDS) features;

(k)     River de-channelization works;

(l)       Construction of noise barriers;

(m)    Woodland Compensation;

(n)     Associated landscaping works;

(o)     Tree felling, transplanting and compensatory planting works;

(p)     Ground investigation, geotechnical and building instrumentation monitoring works; and

(q)     Other works which are shown on the Drawings or specified in the Specifications.

 

1.3        IMPLEMENTATION PROGRAMME

The implementation programme will follow the construction works schedule referred in Appendix A and the location plan is shown in Appendix B.

 

(END)


 

 

  

 

 

 

Appendix A – Construction Works Schedule

 

 

 

 Chart

Description automatically generated

 

 

  

 

Appendix B – Site Location Plan

 

 

 

 

 Diagram, engineering drawing

Description automatically generated

Diagram

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Engineering drawing

Description automatically generated

Diagram

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated